Do NOT start to assemble if you do not have the installation drawings that are provided with the delivery notes.
Panel Planter System is to be installed on a true level surface, free of debris.
- Individual planter panels are numbered and are marked on the on-plan installation drawing.
- Bolt together in a clockwise direction following the numbered panels sequentially,
e.g Panel planter 1 to 15 clockwise. - Bracing as per installation drawing must be positioned but not fully tensioned until the planter is assembled and the planter has some fill applied with equal load to the planter walls. Failure to do so may lead to the planter walls not being 90 degrees to finished floor level.
- The filling of the planter must be from the centre out ensuring equal loads are applied to the planter walls. Failure to do so may lead to the planter walls not being 90 degrees to finished floor level.
- Coping will be supplied in long lengths for installation on site some on site cutting may be required.
- Coping is to be installed after the planter is filled.
Any questions relating to the installation please call 01254 685183 and speak to our Operations team.
Click the image below to download this page as a PDF.